Lord Berkeley to ask Her Majesty's Government, further to the Written Answer by Baroness Sugg on 19 March (HL14551), how many HS2 trains and their destinations an hour per direction are planned to use the connection between HS2 and the West Coast Main Line at Handsacre when (1) only Phase 1 is operational, and (2) both Phases 1 and 2A are operational; and what are the expected dates that Phase 1 and Phase 2 will become operational. HL14724